Power Generation
PROBLEM:
• Critical remote auxiliary gas turbine is rarely used but must be ready immediately when demand arises.
SOLUTION:
• Turbine area now controlled from main control room.
• Redundancy and Instant Failover make sure it’s always ready to be put into action.
A coal-fired power plant added a gas turbine generator to help meet power demand during peak usage periods.
The gas turbine generator has to be ready at all times but is used infrequently enough that it is unmanned.